Letter 198
To adjudicator, enclosing the referral
Special delivery
Dear
We note that you are/have been nominated as [ delete as appropriate ] the
adjudicator. In accordance with clause 9.2 [ substitute '7.2' when using MW or
MWD or '59(2)' when using GC/Works/1 (1998) ] and paragraph 7 of the Scheme
for Construction Contracts (England and Wales) Regulations 1998 [ omit when
using GC/Works/1 (1998) ] we enclose our referral with this letter. Included are
particulars of the dispute or difference, a summary of the contentions on
which we rely, a statement of the relief or remedy sought and further material
which we wish you to consider.
A copy of the referral and the accompanying documentation has been sent to
[ insert name of employer and when using GC/Works/1 (1998) add the names of the
PM and the QS ].
Yours faithfully
Copy: Employer [ add PM and QS when using GC/Works/1 (1998) ] with enclosures
[ The Referral must reach the adjudicator no later than 7 days after the date of the
Notice of Adjudication. ]