Letter 154
To architect, if delay occurs, but no grounds for extension of time
This letter is not suitable for use with MW, MWD or GC/Works/1
(1998).
Dear
The progress of the Works is being/is likely to be [ delete as appropriate ] delayed
due to [ state reasons ].
We will continue to use our best endeavours to minimise the delay and its
effects and we will inform you immediately the cause of the delay has ceased
to operate.
This notice is issued in accordance with clause 2.27.1 [ substitute '2.19.1' when
using IC or ICD or '2.24.1' when using DB ].
Yours faithfully