Letter 131
To architect, enclosing interim application for payment (a)
This letter is only suitable for use with DB.
Dear
Under the provisions of clause 4.9, we enclose an application for interim
payment stating the amount due to us calculated in accordance with
clause 4.13 [ if alternative A applies or substitute '4.14' if alternative B applies ]. In
support of our application we enclose the following details as required under
clause 4.9.3:
[ List ]
We draw your attention to clause 4.10.1 which stipulates that you must pay
the amount stated as due in this application within 14 days of its receipt.
Yours faithfully