Letter 123
To architect, after work opened up for inspection
Dear
We confirm that you inspected [ describe work ] opened up for your inspection
in accordance with your instructions under clause 3.17 [ substitute '3.14' when
using IC or ICD, '3.4' when using MW or MWD, '3.12' when using DB or '40(2)(i)'
when using GC/Works/1 (1998) ]on[ insert date ] and found the materials, goods
and work to be in accordance with the contract.
The cost of opening up and making good, therefore, is to be added to the
contract sum and we will let you have details of our costs within the next
few days. We will shortly send you details, particulars and estimate of the
expected delay in completion of the works beyond the completion date and an
application for reimbursement under the appropriate clause of the contract
[ substitute 'reimbursement for consideration by the employer' when using MW or
MWD ].
Yours faithfully