Letter 115
To architect, on receipt of notice requiring compliance with
instruction (b)
This letter is only suitable for use with GC/Works/1 (1998).
Dear
We have today received your notice dated [ insert date ] which you purport to
issue under the provisions of clause 53 of the conditions of contract.
[ Add either: ]
We will comply with your instruction number [ insert number ], dated [ insert
date ] forthwith, but such compliance is without prejudice to, and reserving,
any other rights and remedies which we may possess.
[ Or: ]
We consider that we have already complied with your instruction number
[ insert number ], dated [ insert date ]. Any attempt by the employer to provide
labour and/or any things, or enter into a contract with others and/or recover
alleged additional costs and expenses from us will be deemed to be a serious
breach of contract for which we will seek appropriate remedies. Without
prejudice to the foregoing, if you will immediately withdraw your notice
requiring compliance, M.. [ insert name ] will be happy to meet you on site
to sort out what appears to be an unfortunate misunderstanding.
[ continued ]