To architect, if oral instruction not confirmed in writing
This letter is only suitable for use with MW or MWD.
Dear
On [ insert date ], you orally instructed us to [ insert the instruction in detail ]. We
have carried out your instruction, as you are aware, but we have not yet
received written confirmation as provided by clause 3.4 of the conditions of
contract. We should be pleased, therefore, if you would send us your written
confirmation immediately.